Critical path to Good Ecological Status

Starting Position (2025)
92 River Water Bodies

  • 12 Good
  • 80 Failing

Important: The sequence below does not imply priority or delivery order. It sets out the logical pathway by which the catchment could achieve Good Ecological Status and the contribution that each intervention is expected to make.

Step 1: Deliver Committed Wastewater Investment
South West Water has already committed to AMP8 and AMP9 investment in 21 sewage treatment works. We estimate that delivery of these schemes could result in 12 river water bodies achieving Good Ecological Status.
Remaining failing RWBs: 68

Step 2: Complete Remaining Priority Wastewater Upgrades
A minimum of 7 additional sewage treatment works are located in catchments where wastewater is the dominant pressure. Phosphate reduction at these assets is likely to be necessary to achieve Good Ecological Status.
Potential additional RWBs reaching Good: 7
Remaining failing RWBs: 61

Step 3: Resolve Suspect Fish Data
The Environment Agency has identified 9 river water bodies with suspect fish data. Based on the wider condition of these river systems, there is a realistic possibility that around 6 river water bodies could be reclassified as Good following updated monitoring.
Potential additional RWBs reaching Good: 6
Remaining failing RWBs: 55

Step 4: Restore Fish Passage
Seven river water bodies appear unlikely to achieve Good status without investment in fish passage and ecological continuity. We estimate that fish passage improvements alone could enable around 5 river water bodies to achieve Good status.
Potential additional RWBs reaching Good: 5
Remaining failing RWBs: 50

Step 5: Address Special Cases
Eight river water bodies are affected by site-specific issues such as mining impacts, heavily modified channels, flow regulation or other non-standard pressures.
We estimate that bespoke interventions alone could restore 4 river water bodies to Good status, while the remaining 4 will also require agricultural interventions.
Potential additional RWBs reaching Good: 4
Remaining failing RWBs: 46

Step 6: Improve Dairy and Beef Slurry Management
Fourteen river water body catchments have high dairy and beef cattle densities and are likely to require targeted slurry management support.

Step 7: Improve Poultry Manure Management
Ten river water body catchments have high poultry densities and are likely to require targeted manure management support.

Step 8: Ongoing Regulatory Enforcement
Targeted regulatory enforcement work focused on compliance with Farming Rules for Water will be needed in 48 river water body catchments

Step 9: Support to Improve Soil Quality and Reduce Runoff
Support programmes (advisory and funding) will be needed to improve soil quality and reduce runoff in 48 river water body catchments

Supporting Interventions

The following interventions are not generally part of the critical path, but are likely to improve outcomes and increase resilience across the catchment.

Riparian Tree Planting - phytobenthos failures appear closely linked to nutrient enrichment. Increasing riverside shading could help reduce algal growth and improve ecological condition in affected water bodies

Fish Habitat Improvement - fish passage alone may not always be sufficient to restore fish populations. Targeted habitat enhancement is likely to accelerate recovery in a number of catchments

Private Sewerage Awareness Programme - private sewerage systems are not generally the determining factor preventing Good Ecological Status in individual river water bodies. However, across the catchment they represent a significant cumulative pressure and would benefit from a targeted awareness and improvement programme

Unit Cost of Interventions

Purpose
This section provides indicative costs for the principal interventions required to deliver Good Ecological Status. Costs are intended for strategic planning purposes and represent typical interventions within a single river water body. Actual costs will vary depending on local site conditions, scale, complexity and delivery approach.

1. Investment in Sewage Treatment Works (phosphate reduction)

Intervention: reduce phosphorus and other pollutant discharges from sewage treatment works through tighter permit standards and investment in treatment infrastructure

Delivery lead: South West Water

Typical cost:

  • Small works: £1m
  • Medium works: £3m
  • Large works: £8m+
  • Average used as assumption: £3m

Funding route: water company investment (AMP programmes)

Cost confidence: medium

2. Investment in Storm Overflows

Intervention: reduce the frequency and duration of storm overflow spills through network upgrades, storage provision and operational improvements

Delivery lead: South West Water

Typical cost:

  • £1m for small project
  • £10m for large project
  • Average used as assumption: £7m per overflow

Funding route: water company investment (AMP programmes)

Cost confidence: medium

3. Regulatory Enforcement

Intervention: Environment Agency inspections, investigation and enforcement activity focused on priority farms

Delivery lead: Environment Agency

Typical cost:

  • 1 dedicated agricultural regulatory officer: £80,000 per year (fully loaded cost, not salary)
  • Typical capacity: 40 farms per year
  • Equivalent cost: £2,000 per farm inspected
  • Assumption used: £2,000 per farm

Funding route: included within existing statutory activity

Cost confidence: medium-high

4. Dairy & Beef Slurry Management Support

Intervention: Support farms to improve slurry handling, storage, treatment and land application

Delivery lead: farmers, advisers, Environment Agency, grant programmes and private finance providers

Typical cost:

  • 1 dedicated farm adviser: £80,000 per year (fully loaded cost, not salary)
  • Typical capacity: 60 farms per year
  • Advisory support: £1,333 per farm
  • Minor infrastructure improvements (yard drainage, clean/dirty water separation, gutters, slurry handling equipment); £5k-£25k
  • Medium infrastructure improvements (slurry store improvements, reception pits, transfer systems and dirty water management): £25k-£75k
  • Major infrastructure improvements (new slurry lagoons, major storage infrastructure and whole-farm redesign): £75k-£250k+
  • Average assumption used (advisory support and infrastructure): £30,000 per farm

Funding route: farmer investment, DEFRA slurry infrastructure grants, water company catchment programmes, eNGO programmes and private finance

Cost confidence: medium

Notes: the £30,000 assumption reflects the average level of investment likely to be required across a portfolio of priority livestock farms. Most farms will require minor or medium infrastructure improvements, while a smaller number will require major slurry storage upgrades costing substantially more

5. Poultry Manure Management Support

Intervention: improve the storage, transport, treatment and land application of poultry manure to reduce nutrient losses to watercourses.

Delivery lead: farmers, advisers, poultry integrators, Environment Agency

Typical cost:

  • 1 dedicated farm adviser: £80,000 per year (fully loaded cost, not salary)
  • Typical capacity: 60 farms per year
  • Advisory support: £1,333 per farm
  • Improved storage, handling and nutrient planning: £10,000-£25,000 per farm
  • Manure processing, treatment or export infrastructure: £25,000-£100,000 per farm
  • Average assumption used (advisory support and infrastructure): £25,000 per farm

Funding route: farmer investment, DEFRA productivity and infrastructure grants, poultry supply chain investment, water company catchment programmes, eNGO programmes and private finance

Cost confidence: medium

Note: the £25,000 assumption reflects the average level of investment likely to be required across a portfolio of priority poultry farms. Most farms will require improvements to manure handling, storage, transport and nutrient planning, while a smaller number will require more significant manure processing, treatment or export infrastructure.

6. Soil Health & Runoff Reduction

Intervention: improve soil health and reduce runoff through increasing soil cover and living roots, improving crop and grassland diversity, minimising soil disturbance and compaction, improving grazing and stocking management, increasing soil organic matter, managing runoff pathways and monitoring soil condition.

Delivery lead: farmers, advisers, catchment partnerships, grant programmes and private finance providers

Typical cost:

  • 1 dedicated farm adviser: £80,000 per year (fully loaded cost, not salary)
  • Typical capacity: 60 farms per year
  • Advisory support: £1,333 per farm
  • Lighter-touch intervention (soil planning, nutrient planning): £50-150 per hectare per year for 3 years
  • Typical catchment-sensitive farming package: £150-300 per hectare per year for 3 years
  • Intensive package (buffer strips, herbal leys, low-input grassland, cover crops, etc.): £300-600 per hectare per year for 3 years
  • Typical intervention area: 25-50 hectares per priority farm
  • Average assumption used: £28,000 per priority farm (equivalent to 30 hectares receiving support at £300/ha/year for three years, plus adviser support)

Funding route: farmer investment, SFI/ELM schemes, private finance

Cost confidence: low-medium

7. Fish Data & Investigation

Intervention: undertake fish population surveys, classification reviews and targeted investigations to confirm or challenge current fish status classifications and improve understanding of fish population pressures

Delivery lead: Environment Agency, West Country Rivers Trust, fisheries specialists

Typical cost:

  • Desktop review of existing evidence: £1,000-£2,000 per river water body
  • Fish survey (electrofishing and reporting): £3,000-£5,000 per river water body
  • Classification review and EA engagement: £1,000-£2,000 per river water body
  • Average assumption used: £6,000 per river water body

Funding route: Environment Agency monitoring programmes, catchment partnerships, fisheries programmes, charitable grants and research funding

Cost confidence: high

8. Fish Passage & Ecological Continuity

Intervention: assess and remove barriers to fish movement or install fish passage solutions

Delivery lead: West Country Rivers Trust, Environment Agency, asset owners

Typical cost:

  • Assessment & options appraisal: £5,000 per barrier
  • Detailed design & permissions: £50,000-£100,000 per barrier
  • Physical delivery:
    • Removal: £50,000-£150,000
    • Simple pass: £150,000-£500,000
    • Technical pass: £500,000-£1.5m+
  • Average assumption used: £500,000 per barrier

Funding route: Environment Agency, river restoration programmes, water company catchment investment, National Lottery, charitable trusts, environmental grants and private finance

Cost confidence: low-medium

9. Special Cases

Intervention: bespoke responses to mining impacts, specific pollutants, heavily modified channels and other non-standard pressures.

Delivery lead: site specific

Typical cost:

  • Feasibility & investigation: £10,000-£50,000 per RWB
  • Detailed design & appraisal: £25,000-£100,000 per RWB
  • Physical works: highly variable
  • Average assumption used: £250,000 per RWB

Funding route: site-specific combination of public funding, regulatory investment, environmental grants and private finance

Cost confidence: low

10. Riparian Tree Planting

Intervention: establish riparian woodland and increase river shading to reduce algal growth, improve water temperature resilience, reduce bank erosion and support ecological recovery

Delivery lead: landowners, North Devon Biosphere Foundation (Devon Woods programme), Westcountry Rivers Trust, Devon Wildlife Trust, National Trust

Typical cost:

  • 1 dedicated farm adviser: £80,000 per year (fully loaded cost, not salary)
  • Typical capacity: 40 farms per year
  • Advisory support: £2,000 per woodland project
  • Assumption: 1 hectare of riparian woodland creation per participating landowner (projects will also likely include non riparian together with the riparian); 1 hectare of riparian woodland is broadly equivalent to 1 kilometre of planting at an average width of 10 metres along a single river bank
  • Capital establishment cost: £12,000 per hectare
  • Maintenance cost: £400 per hectare per year for 15 years = £6,000 per hectare
  • Average assumption used: £20,000 per participating landowner (equivalent to 1 hectare of riparian woodland creation plus advisory support)

Funding route: England Woodland Creation Offer (EWCO), woodland grants, SFI/ELM schemes, water company catchment programmes, biodiversity funding and private finance

Cost confidence: medium

Note: woodland creation schemes typically provide both establishment and long-term maintenance funding. The £20,000 assumption reflects the full support package required to establish and maintain 1 hectare of riparian woodland over the initial 15-year maintenance period.

11. Fish Habitat Improvement

Intervention: improve fish populations through gravel augmentation, woody debris introduction, refuge habitat creation, bank restoration, channel diversification and targeted in-stream habitat enhancements.

Delivery lead: Westcountry Rivers Trust, Environment Agency, fisheries groups, landowners and catchment partnerships

Typical cost:

  • Habitat assessment and design: £5,000-£10,000 per river water body
  • Targeted habitat improvement works: £15,000-£90,000 per river water body
  • Average assumption used: £50,000 per river water body

Funding route: Environment Agency fisheries programmes, river restoration programmes, water company catchment investment, charitable trusts, environmental grants and private finance

Cost confidence: low-Medium

Note: fish habitat improvement is intended to complement fish passage improvements rather than replace them. It is most likely to be effective where barriers to movement have already been removed or mitigated.

12. Private Sewerage Awareness & Improvement Programme

Intervention: increase awareness, maintenance and compliance of private sewerage systems through targeted communications, inspections, advice and support for priority properties

Delivery lead: Local authorities, Environment Agency, catchment partnerships, NGOs and householders

Typical cost:

  • Awareness campaign and communications: £2,000-£5,000 per operational catchment
  • Technical advice and inspections: £250-£500 per priority property
  • Improvement grants for priority properties: £2,000-£5,000 per property
  • Average assumption used: £10,000 per operational catchment

Funding route: Local authorities, catchment partnerships, charitable grants, household investment and private finance.

Cost confidence: medium

Note: this intervention focuses on awareness, maintenance and targeted improvements to priority properties. It does not assume wholesale replacement of private sewerage systems across a catchment

Intervention Summary

What the analysis tells us

  • The challenge is large: achieving Good Ecological Status across North Devon requires an estimated £387.9 million of intervention investment
  • Most of the funding route already exists: we estimate that 95% (£368.9 million) can be delivered through existing programmes and recognised funding mechanisms
  • The true funding gap is relatively small: around £18.9 million remains without an obvious delivery mechanism
  • The real challenge is coordination: aligning existing funding, regulatory activity and delivery programmes with the river water bodies where they will have the greatest impact
  • North Devon does not need to invent a new recovery system: much of the infrastructure, expertise, funding and delivery capacity already exists
  • Success will depend on filling a small number of strategic gaps, particularly around slurry management, poultry manure, fisheries recovery and bespoke interventions for special-case river water bodies
Intervention No. of RWBs Estimated Cost % Available % Delivered Lead
Priority interventions (not in order of priority)
1. Investment in STWs (phosphate reduction) 40 £120m 100% 0% SWW
2. Investment in storm overflows (reduction in spills) 33 £231m 100% 0% SWW
3. Regulatory enforcement to drive compliance with Farming Rules for Water 48 £1.3m 100% Data to follow EA
4. Dairy/beef cattle slurry management support 14 £7.3m 20% 0% ?
5. Poultry manure management support 10 £1.5m 20% 0% ?
6. Soil health interventions 48 £18m 67% 0% DWT/WRT
7. Fish data 9 £54,000 0% 0% WRT
8. Removing barriers 7 £3.5m 0% 0% WRT
9. Special case interventions 8 £2m 0% 0% ?
Total: c.£384.7m, of which c.£366.1m available, and c.£18.5m to be found
Secondary interventions
10. Riparian tree planting 48 £2.7m 100% 0% NDBF
11. Fish habitat improvement 8 £400,000 0% 0% WRT
12. Private sewerage awareness & improvement programme 17 £170,000 0% 0% ?
Total: c.£3.3m, of which c.£2.7m available, and c.£0.6m to be found
Overall total: c.£387.9m, of which c.£368.8m available, and c.£19.1m to be found

Interventions Detail

1. Investment in STWs (phosphate reduction)

Investment in STWs (phosphate reduction)
DescriptionReduce phosphorus and other pollutant discharges from sewage treatment works through tighter permit standards and investment in treatment infrastructure.
Lead delivery organisationSouth West Water
No. of river water bodies13 highest priority, 27 secondary priority
Estimated total cost£120m
Funding available£120m (£42m already secured in AMP8 & AMP9)
Funding gap£0m
Funding route / sourceWater company investment (AMP programmes)
Ecological benefitReduce phosphorus loading from wastewater, improve phosphate and phytobenthos status.
Confidence in costingsMedium (£3m is a very broad average)

Progress

  • South West Water have plans to invest in sewage treatment works to reduce phosphate level in 48 river water bodies
  • The funding for this is agreed in 5-year investment periods; AMP8 is 2025-2030 and is currently being delivered ; there are 5 river water bodies that will see reductions in phosphate from AMP8 investments at an estimated total cost of £15 million
  • AMP9 (2030-2035) is still subject to consultation; South West Water are currently planning investment in phosphate reduction in 17 river water bodies in AMP9 at an estimated total cost of £51 million
  • Having made these investments, there are 7 river water bodies that will definitely require investment in sewage treatment works to reduce phosphate levels; these should be the priority for any further changes to AMP9, and then for AMP10 (2035-2040); this would cost c.£21 million
  • In addition, there are 19 river water bodies where wastewater phosphate forms part of mixed pressure signature, along with agriculture pressures. While sewage treatment works investment is necessary in these catchments, it is unlikely to be sufficient on its own to achieve Good Ecological Status and will need to be combined with agricultural interventions. Investment in these river water bodies in AMP10 (2035-204) would cost an estimated £57 million
  • All funding is currently classified as available because a recognised delivery mechanism exists through successive water company investment periods (AMP8, AMP9 and AMP10). While not all funding has yet been formally approved, there is a clear and established route to securing investment through the regulated water industry planning process

Highest Priority, as Predominantly Waste Water Issue

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Chelfham Stream £3m £3m 2030-2035 SWW
Coney Gut AMP9 £3m £3m 2030-2035 SWW
Dipple Water £3m SWW
Dolton Stream £3m SWW
Kenwith Stream AMP8 £3m £3m 2025-2030 SWW
Knowl Water AMP9 £3m £3m 2030-2035 SWW
Little Mere River AMP9 £3m £3m 2030-2035 SWW
Mully Brook £3m SWW
Newton Tracey Stream £3m SWW
Taw (Bullow Brook to River Yeo) £3m SWW
Taw (Source to Bullow Brook) AMP9 £3m £3m 2030-2035 SWW
Whitsleigh Down Brook £3m SWW
Woolleigh Brook £3m SWW

Secondary Priority, as Mixed Waste Water and Agricultural Issues

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River AMP8 £3m £3m 2025-2030 SWW
Bullow Brook AMP9 £3m £3m 2030-2035 SWW
Combe Lake £3m SWW
Crooked Oak £3m SWW
Hawkridge Brook AMP9 £3m £3m 2030-2035 SWW
Hollocombe Water £3m SWW
Horwood Stream £3m SWW
Iddesleigh Stream £3m SWW
Knighty Brook AMP8 £3m £3m 2025-2030 SWW
Langham Lake AMP9 £3m £3m 2030-2035 SWW
Langtree Lake £3m SWW
Little Silver Stream £3m SWW
Lower Little River Dart £3m SWW
Lower River Lew (Torridge) AMP9 £3m £3m 2030-2035 SWW
Lower River Yeo (Bideford) £3m SWW
Lower River Yeo (Lapford) £3m SWW
Mole (Source to Burcombe Stream) £3m SWW
Mole (Taw to Bray) £3m SWW
Mole (Yeo to Burcombe Stream) £3m SWW
Northlew Stream AMP9 £3m £3m 2030-2035 SWW
Pulworthy Brook AMP8 £3m £3m 2025-2030 SWW

Others Included in SWW’s AMP8 (2025-2030) or AMP9 (2030-2035) Investment Programme

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradwell Stream AMP9 £3m £3m 2030-2035 SWW
Hole Brook AMP9 £3m £3m 2030-2035 SWW
Lower Caen AMP9 £3m £3m 2030-2035 SWW
Middle River Okement AMP9 £3m £3m 2030-2035 SWW
Torridge (Combe Lake to Lew) AMP9 £3m £3m 2030-2035 SWW
Upper River Yeo (Lapford) AMP9 £3m £3m 2025-2030 SWW
Waldon AMP9 £3m £3m 2030-2035 SWW

2. Investment in storm overflows (reduction in spills)

Investment in storm overflows (reduction in spills)
DescriptionReduce the frequency and duration of storm overflow discharges through investment in natural flood management measures, sewerage infrastructure and network performance.
Lead delivery organisationSouth West Water
No. of river water bodies33
Estimated total cost£231 million
Funding available£231 million
Funding gap£0
Funding route / sourceAMP 8-10
Ecological benefitReduced wastewater pollution from storm overflow spills, improving water quality, supporting ecological recovery, reducing public health risks associated with sewage contamination, and improving confidence in the safety and enjoyment of rivers for recreation and angling.
Confidence in costingsMedium

Progress

  • South West Water have plans invest in all storm overflows that are regularly spilling, with a target to bring them down to less than 12 spills per year
  • These investments are prioritised across investment periods
  • AMP8 (2025-2030) prioritises storm overflows impacting shellfish waters, bathing waters and ecologically sensitive stretches of river; this includes 5 river water bodies at an estimated cost of £35 million
  • AMP9 (2030-2035) remains subject to consultation and regulatory approval; South West Water are currently planning storm overflow investment affecting 19 river water bodies at an estimated cost of £133 million
  • The remaining storm overflows required to achieve the less-than-12-spills-per-year target would then be addressed through AMP10 (2035-2040). We currently identify 9 river water bodies with high or very high spill frequencies that should be prioritised for acceleration into AMP9 where feasible
  • All funding is currently classified as available because a recognised delivery mechanism exists through successive water company investment periods (AMP8, AMP9 and AMP10). While not all funding has yet been formally approved, there is a clear and established route to securing investment through the regulated water industry planning process

Priority Because of Impact on Shellfish Waters, Bathing Waters, and Ecologically Sensitive Stretches of River

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Hawkridge Brook AMP9 £7m £7m 2030 2035 SWW
Kenwith Stream AMP8 £7m £7m 2025 2030 SWW
Knowl Water AMP8 £7m £7m 2025 2030 SWW
Mole (Yeo to Burcombe Stream) AMP8 £7m £7m 2025 2030 SWW
Nadrid Water AMP9 £7m £7m 2030 2035 SWW
Umber AMP8 £7m £7m 2025 2030 SWW
West Lyn River AMP8 £7m £7m 2025 2030 SWW

Secondary Priority Because of Very High or High Spill Duration per Year

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River £7m No No SWW
Bradiford Water AMP9 £7m £7m 2030 2035 SWW
Bray (Mole to Hole Water) AMP9 £7m £7m 2030 2035 SWW
Bray (Source to Hole Water) AMP9 £7m £7m 2030 2035 SWW
Chelfham Stream £7m No No SWW
Dolton Stream £7m No No SWW
Duntz AMP9 £7m £7m 2030 2035 SWW
Langham Lake AMP9 £7m £7m 2030 2035 SWW
Little Mere River AMP9 £7m £7m 2030 2035 SWW
Lower Caen £7m No No SWW
Lower Little River Dart AMP9 £7m £7m 2030 2035 SWW
Lower River Lew (Torridge) AMP9 £7m £7m 2030 2035 SWW
Middle River Okement AMP9 £7m £7m 2030 2035 SWW
Mole (Source to Burcombe Stream) AMP9 £7m £7m 2030 2035 SWW
Mully Brook AMP9 £7m £7m 2030 2035 SWW
Pulworthy Brook AMP9 £7m £7m 2030 2035 SWW
Taw (River Mole to Estuary) AMP9 £7m £7m 2030 2035 SWW
Taw (River Yeo to Little Dart River) £7m No No SWW
Taw (Source to Bullow Brook) £7m No No SWW
Torridge (Combe Lake to Lew) AMP9 £7m £7m 2030 2035 SWW
Torridge (Lew to Estuary) AMP9 £7m £7m 2030 2035 SWW
Upper River Mere £7m No No SWW
Upper River Yeo (Bideford) AMP9 £7m £7m 2030 2035 SWW
Upper River Yeo (Lapford) £7m No No SWW
Whitsleigh Down Brook AMP9 £7m £7m 2030 2035 SWW
Woolleigh Brook £7m No No SWW

3. Regulatory enforcement to drive compliance with Farming Rules for Water

Regulatory enforcement to drive compliance with Farming Rules for Water
DescriptionEnvironment Agency inspections, investigation and enforcement activity focused on priority farms.
Lead delivery organisationEnvironment Agency
No. of river water bodies48 (21 priority, 27 secondary)
Estimated total cost£1.3 million (equivalent to inspecting & engaging 645 farms)
Funding available£1.3 million
Funding gap£0
Funding route / sourceIncluded within existing statutory activity
Ecological benefitReduced nutrient, sediment and faecal pollution from agriculture through improved compliance, contributing to improved phosphate status and reduced phytobenthos failures.
Confidence in costingsMedium-high

Progress

  • The Environment Agency currently has 2 regulatory enforcement officers active in the North Devon Management Catchment, each with a target of inspecting and working with 40 farms per year; this level of activity was started in 2025
  • We estimate that inspections and engagements at 645 farms within priority or secondary priority river water bodies will be needed to drive towards Good Ecological Status; with 2 regulatory enforcement officers and 40 farms per year, this will take c.8 years
  • We would advocate for investment in a third, and potentially a fourth, regulatory enforcement officer. This would represent a relatively low-cost intervention with the potential to significantly accelerate delivery across agricultural catchments
  • We have classified the funding as available because regulatory enforcement forms part of the Environment Agency's existing statutory responsibilities. The current level of resource is sufficient to deliver the intervention over time, although additional officer capacity would significantly accelerate delivery and increase the likelihood of achieving Good Ecological Status within a shorter timeframe

Priority as Predominantly Agricultural Issue

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradwell Stream c.8 priority farms £16,000 £16,000 Yes No EA
Burcombe Stream c.5 priority farms £10,000 £10,000 Yes No EA
Dalch c.25 priority farms £50,000 £50,000 Yes No EA
Duntz c.15 priority farms £30,000 £30,000 Yes No EA
Hole Brook c.30 priority farms £60,000 £60,000 Yes No EA
Huntshaw Water c.10 priority farms £20,000 £20,000 Yes No EA
Lower Caen c.7 priority farms £14,000 £14,000 Yes No EA
Lower River Okement c.2 priority farms £4,000 £4,000 Yes No EA
Medland Brook c.7 priority farms £14,000 £14,000 Yes No EA
Middle River Lew (Torridge) c.3 priority farms £6,000 £6,000 Yes No EA
Middle River Okement c.20 priority farms £40,000 £40,000 Yes No EA
Mole (Bray to Yeo) c.8 priority farms £16,000 £16,000 Yes No EA
Mussel Brook c.11 priority farms £22,000 £22,000 Yes No EA
Nadrid Water c.6 priority farms £12,000 £12,000 Yes No EA
Philham Water c.4 priority farms £8,000 £8,000 Yes No EA
Torridge (Combe Lake to Lew) c.28 priority farms £56,000 £56,000 Yes No EA
Torridge (Lew to Estuary) c.24 priority farms £48,000 £48,000 Yes No EA
Torridge (Source to Dipple Water) c.18 priority farms £36,000 £36,000 Yes No EA
Upper River Lew (Torridge) c.18 priority farms £36,000 £36,000 Yes No EA
Upper River Yeo (Lapford) c.31 priority farms £62,000 £62,000 Yes No EA
Waldon c.35 priority farms £70,000 £70,000 Yes No EA

Secondary Priority, as Mixed Waste Water and Agricultural Issues

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River c.6 priority farms £12,000 £12,000 Yes No EA
Bullow Brook c.6 priority farms £12,000 £12,000 Yes No EA
Combe Lake c.7 priority farms £14,000 £14,000 Yes No EA
Crooked Oak c.21 priority farms £42,000 £42,000 Yes No EA
Hawkridge Brook c.10 priority farms £20,000 £20,000 Yes No EA
Hollocombe Water c.11 priority farms £22,000 £22,000 Yes No EA
Horwood Stream c.7 priority farms £14,000 £14,000 Yes No EA
Iddesleigh Stream c.5 priority farms £10,000 £10,000 Yes No EA
Knighty Brook c.16 priority farms £32,000 £32,000 Yes No EA
Langham Lake c.17 priority farms £34,000 £34,000 Yes No EA
Langtree Lake c.9 priority farms £18,000 £18,000 Yes No EA
Little Silver Stream c.17 priority farms £34,000 £34,000 Yes No EA
Lower Little River Dart c.29 priority farms £58,000 £58,000 Yes No EA
Lower River Lew (Torridge) c.7 priority farms £14,000 £14,000 Yes No EA
Lower River Yeo (Bideford) c.5 priority farms £10,000 £10,000 Yes No EA
Lower River Yeo (Lapford) c.5 priority farms £10,000 £10,000 Yes No EA
Mole (Source to Burcombe Stream) c.14 priority farms £28,000 £28,000 Yes No EA
Mole (Taw to Bray) c.11 priority farms £22,000 £22,000 Yes No EA
Mole (Yeo to Burcombe Stream) c.4 priority farms £8,000 £8,000 Yes No EA
Northlew Stream c.9 priority farms £18,000 £18,000 Yes No EA
Pulworthy Brook c.13 priority farms £26,000 £26,000 Yes No EA
Taw (Little Dart River to River Mole) c.9 priority farms £18,000 £18,000 Yes No EA
Taw (River Mole to Estuary) c.36 priority farms £72,000 £72,000 Yes No EA
Taw (River Yeo to Little Dart River) c.16 priority farms £32,000 £32,000 Yes No EA
Upper Little Dart River c.17 priority farms £34,000 £34,000 Yes No EA
Upper River Mere c.9 priority farms £18,000 £18,000 Yes No EA
Upper River Yeo (Bideford) c.14 priority farms £28,000 £28,000 Yes No EA

4. Dairy/beef cattle slurry management support

Dairy/beef cattle slurry management support
DescriptionSupport farms to improve slurry handling, storage, treatment and land application.
Lead delivery organisationFarmers, advisers, Environment Agency, grant programmes and private finance providers.
No. of river water bodies14
Estimated total cost£7.3 million
Funding available£1.5 million
Funding gap£5.8 million
Funding route / sourceNot yet clear
Ecological benefitReduce phosphorus losses from livestock farming and improve phosphate and phytobenthos status.
Confidence in costingsLow-medium

Progress

  • There are generalist farm advisory programmes active across Northern Devon (Natural England, Devon Wildlife Trust, Westcountry Rivers Trust and North Devon Plus), but none are explicitly focused on beef and dairy cattle farms and slurry management. Advisory support is available, but current provision is fragmented and not aligned to the priority river water bodies identified through Catchment Catalyst
  • The UK Government has previously funded slurry infrastructure improvements through schemes such as the Slurry Infrastructure Grant, providing capital support for additional slurry storage and associated infrastructure. However, the programme has operated through periodic funding rounds rather than as a permanent open scheme, creating uncertainty around future access to capital funding and making long-term planning difficult for farmers
  • Additional support has historically been available through the Countryside Stewardship Capital Grant programme for some pollution reduction and water quality measures. However, access to these grants is often linked to the work of the Catchment Sensitive Farming team, whose resources are limited and currently focused on a small number of priority catchments each year. Demand for capital grants has also frequently exceeded available funding
  • There is currently no dedicated North Devon programme focused specifically on slurry management within priority river water body catchments. As a result, support is fragmented across advisory, regulatory and grant-funded initiatives
  • Designing and securing funding for a dedicated slurry management programme should be considered a priority. We estimate that approximately 245 priority livestock farms fall within the 14 target river water body catchments. Delivering tailored advice and infrastructure improvements across these farms is likely to require a multi-year programme combining advisory support, grant funding, farmer investment and private finance
  • Based on current funding mechanisms, we estimate that approximately 20% of the required investment could potentially be met through existing grant programmes and farm co-investment, leaving a significant funding gap that would require a dedicated catchment-scale funding programme to address

Priority Farms Capital Improvements

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradwell Stream c.10 priority farms £300,000 £0 No No To establish
Bullow Brook c.15 priority farms £450,000 £0 No No To establish
Combe Lake c.11 priority farms £330,000 £0 No No To establish
Duntz c.30 priority farms £900,000 £0 No No To establish
Knighty Brook c.20 priority farms £600,000 £0 No No To establish
Langtree Lake c.10 priority farms £300,000 £0 No No To establish
Lower River Okement c.7 priority farms £210,000 £0 No No To establish
Lower River Yeo (Bideford) c.6 priority farms £240,000 £0 No No To establish
Medland Brook c.14 priority farms £420,000 £0 No No To establish
Mussel Brook c.9 priority farms £270,000 £0 No No To establish
Northlew Stream c.8 priority farms £240,000 £0 No No To establish
Philham Water c.13 farms £420,000 £0 No No To establish
Upper River Yeo (Bideford) c.18 farms £540,000 £0 No No To establish
Waldon c.68 farms £2.04m £0 No No To establish

5. Poultry manure management support

Poultry manure management support
DescriptionImprove the storage, transport, treatment and land application of poultry manure to reduce nutrient losses to watercourses.
Lead delivery organisationFarmers, advisers, poultry integrators, Environment Agency, grant programmes and private finance providers.
No. of river water bodies10
Estimated total cost£1.9 million
Funding available£0.4 million
Funding gap£1.5 million
Funding route / sourceFarmer investment, poultry supply chains, grants, water company catchment programmes and private finance.
Ecological benefitReduce phosphorus losses from poultry farming and improve phosphate and phytobenthos status.
Confidence in costingsLow-medium

Progress

  • There are generalist farm advisory programmes active across Northern Devon (Natural England, Devon Wildlife Trust, Westcountry Rivers Trust and North Devon Plus), but none are specifically focused on poultry manure management within poultry-intensive catchments
  • Existing support is largely targeted at nutrient management and regulatory compliance rather than the systematic management of poultry manure surpluses at catchment scale. As a result, there is currently no coordinated programme addressing the movement, treatment, processing and application of poultry manure across priority river water body catchments
  • Some support may be available through existing grant programmes, including Countryside Stewardship Capital Grants, Catchment Sensitive Farming support and wider pollution reduction initiatives. However, these schemes were not designed specifically to address poultry manure pressures and are unlikely to provide funding at the scale required
  • Delivery is further complicated by the fact that the environmental impact of poultry enterprises is often concentrated within a relatively small number of holdings, requiring bespoke solutions rather than generic farm advice
  • Designing and securing funding for a dedicated poultry manure management programme should be considered a priority. We estimate that approximately 74 priority poultry farms fall within the 10 target river water body catchments. Delivering tailored advice, nutrient planning, manure handling improvements, treatment infrastructure and manure export arrangements across these farms is likely to require a multi-year programme combining advisory support, grant funding, poultry supply-chain investment and private finance
  • Based on current funding mechanisms, we estimate that approximately 20% of the required investment could potentially be met through existing grant programmes, farm investment and poultry supply-chain contributions, leaving a substantial funding gap that would require a dedicated catchment-scale programme to address

Poultry Manure Management Support - Priority River Water Bodies

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Burcombe Stream c.2 priority farms £50,000 £0 No No To establish
Dalch c.15 priority farms £375,000 £0 No No To establish
Hollocombe Water c.12 priority farms £300,000 £0 No No To establish
Huntshaw Water c.3 priority farms £75,000 £0 No No To establish
Iddesleigh Stream c.3 priority farms £75,000 £0 No No To establish
Lower Little River Dart c.14 priority farms £350,000 £0 No No To establish
Mole (Source to Burcombe Stream) c.4 priority farms £100,000 £0 No No To establish
Nadrid Water c.2 priority farms £50,000 £0 No No To establish
Upper Little Dart River c.6 priority farms £150,000 £0 No No To establish
Waldon c.13 priority farms £325,000 £0 No No To establish

6. Soil health interventions

Soil health interventions
DescriptionProvide advisory support and funding to farms, to improve soil health and reduce runoff, through: increasing soil cover and living roots, improving crop and grassland diversity, minimising soil disturbance and compaction, improving grazing and stocking management, increasing soil organic matter, managing runoff pathways and monitoring soil condition.
Lead delivery organisationNatural England, DWT, WRT, EA
No. of river water bodies48 (21 priority, 27 secondary)
Estimated total cost£18.0m (equivalent to supporting 645 farms)
Funding available£12.0m
Funding gap£6.0m
Funding route / sourceFarmer investment, SFI/ELM schemes, private finance
Ecological benefitLess phosphorous, less sediment, improved phytobenthos and macroinvertebrate communities, enhanced fish habitat quality, and greater catchment resilience to drought and high rainfall events. Additional co-benefits include increased soil carbon, improved soil health and reduced downstream flood risk.
Confidence in costingsLow-medium

Progress

  • We estimate that support is required at approximately 645 farms within the 48 target river water body catchments, at a total cost of £18.0 million. Delivering soil health and runoff reduction measures across these farms would require a combination of advisory support, environmental land management payments, targeted capital grants and private finance over a number of years
  • There are a range of farm advisory programmes active across Northern Devon, including support delivered by Natural England, Devon Wildlife Trust, Westcountry Rivers Trust and North Devon Plus (although some of these programmes require continuation funding). In addition, the Catchment Sensitive Farming team provides dedicated support within two priority river water body catchments each year. Together, these programmes already provide a substantial proportion of the advisory capacity required to support soil health and runoff reduction measures
  • Government funding is available through the Sustainable Farming Incentive (SFI), which supports many of the measures identified within this intervention, including cover crops, herbal leys, low-input grassland, buffer strips, nutrient management and soil planning. Additional support has historically been available through the Countryside Stewardship Capital Grant programme for practical runoff reduction measures such as sediment traps, livestock management infrastructure, watercourse fencing and alternative drinking water supplies. However, access to these schemes can be constrained by advisory capacity, eligibility requirements and the fact that demand has often exceeded available funding
  • In addition, there is emerging evidence of soil carbon markets providing a potential private-finance route for some farms, creating opportunities to blend public and private funding sources where improvements in soil health can be measured and verified
  • The principal challenge is therefore not the absence of funding mechanisms, but ensuring that advisory support and financial incentives are targeted towards the highest-priority farms and river water bodies identified through Catchment Catalyst
  • Based on current funding mechanisms, we estimate that c.66% of the £18.0 million investment requirement could potentially be met through existing Government schemes and emerging private-finance mechanisms over a 10-year period, leaving a significant but potentially bridgeable funding gap

Priority as Predominantly Agricultural Issue

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradwell Stream c.8 priority farms £224,000 £0 No No NE/DWT/WRT/EA
Burcombe Stream c.5 priority farms £140,000 £0 No No NE/DWT/WRT/EA
Dalch c.25 priority farms £700,000 £0 No No NE/DWT/WRT/EA
Duntz c.15 priority farms £420,000 £0 No No NE/DWT/WRT/EA
Hole Brook c.30 priority farms £840,000 £0 No No NE/DWT/WRT/EA
Huntshaw Water c.10 priority farms £280,000 £0 No No NE/DWT/WRT/EA
Lower Caen c.7 priority farms £196,000 £0 No No NE/DWT/WRT/EA
Lower River Okement c.2 priority farms £56,000 £0 No No NE/DWT/WRT/EA
Medland Brook c.7 priority farms £196,000 £0 No No NE/DWT/WRT/EA
Middle River Lew (Torridge) c.3 priority farms £84,000 £0 No No NE/DWT/WRT/EA
Middle River Okement c.20 priority farms £560,000 £0 No No NE/DWT/WRT/EA
Mole (Bray to Yeo) c.8 priority farms £224,000 £0 No No NE/DWT/WRT/EA
Mussel Brook c.11 priority farms £304,000 £0 No No NE/DWT/WRT/EA
Nadrid Water c.6 priority farms £168,000 £0 No No NE/DWT/WRT/EA
Philham Water c.4 priority farms £112,000 £0 No No NE/DWT/WRT/EA
Torridge (Combe Lake to Lew) c.28 priority farms £784,000 £0 No No NE/DWT/WRT/EA
Torridge (Lew to Estuary) c.24 priority farms £672,000 £0 No No NE/DWT/WRT/EA
Torridge (Source to Dipple Water) c.18 priority farms £504,000 £0 No No NE/DWT/WRT/EA
Upper River Lew (Torridge) c.18 priority farms £504,000 £0 No No NE/DWT/WRT/EA
Upper River Yeo (Lapford) c.31 priority farms £868,000 £0 No No NE/DWT/WRT/EA
Waldon c.35 priority farms £980,000 £0 No No NE/DWT/WRT/EA

Secondary Priority, as Mixed Waste Water and Agricultural Issues

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River c.6 priority farms £168,000 £0 No No NE/DWT/WRT/EA
Bullow Brook c.6 priority farms £168,000 £0 No No NE/DWT/WRT/EA
Combe Lake c.7 priority farms £196,000 £0 No No NE/DWT/WRT/EA
Crooked Oak c.21 priority farms £588,000 £0 No No NE/DWT/WRT/EA
Hawkridge Brook c.10 priority farms £280,000 £0 No No NE/DWT/WRT/EA
Hollocombe Water c.11 priority farms £308,000 £0 No No NE/DWT/WRT/EA
Horwood Stream c.7 priority farms £196,000 £0 No No NE/DWT/WRT/EA
Iddesleigh Stream c.5 priority farms £140,000 £0 No No NE/DWT/WRT/EA
Knighty Brook c.16 priority farms £448,000 £0 No No NE/DWT/WRT/EA
Langham Lake c.17 priority farms £476,000 £0 No No NE/DWT/WRT/EA
Langtree Lake c.9 priority farms £252,000 £0 No No NE/DWT/WRT/EA
Little Silver Stream c.17 priority farms £476,000 £0 No No NE/DWT/WRT/EA
Lower Little River Dart c.29 priority farms £812,000 £0 No No NE/DWT/WRT/EA
Lower River Lew (Torridge) c.7 priority farms £196,000 £0 No No NE/DWT/WRT/EA
Lower River Yeo (Bideford) c.5 priority farms £140,000 £0 No No NE/DWT/WRT/EA
Lower River Yeo (Lapford) c.5 priority farms £140,000 £0 No No NE/DWT/WRT/EA
Mole (Source to Burcombe Stream) c.14 priority farms £392,000 £0 No No NE/DWT/WRT/EA
Mole (Taw to Bray) c.11 priority farms £308,000 £0 No No NE/DWT/WRT/EA
Mole (Yeo to Burcombe Stream) c.4 priority farms £112,000 £0 No No NE/DWT/WRT/EA
Northlew Stream c.9 priority farms £252,000 £0 No No NE/DWT/WRT/EA
Pulworthy Brook c.13 priority farms £364,000 £0 No No NE/DWT/WRT/EA
Taw (Little Dart River to River Mole) c.9 priority farms £252,000 £0 No No NE/DWT/WRT/EA
Taw (River Mole to Estuary) c.36 priority farms £1.01m £0 No No NE/DWT/WRT/EA
Taw (River Yeo to Little Dart River) c.16 priority farms £448,000 £0 No No NE/DWT/WRT/EA
Upper Little Dart River c.17 priority farms £476,000 £0 No No NE/DWT/WRT/EA
Upper River Mere c.9 priority farms £252,000 £0 No No NE/DWT/WRT/EA
Upper River Yeo (Bideford) c.14 priority farms £392,000 £0 No No NE/DWT/WRT/EA

7. Fish data

Fish data
DescriptionCollection of new fish data to target river water bodies where the Environment Agency recognises its fish data is suspect.
Lead delivery organisationWest Country Rivers Trust, Environment Agency
No. of river water bodies9
Estimated total cost£54,000
Funding available£0
Funding gap£54,000
Funding route / sourceEnvironment Agency monitoring programmes, catchment partnerships, fisheries programmes, charitable grants and research funding.
Ecological benefitNone – improved confidence in fish data.
Confidence in costingsHigh

Progress

  • The Westcountry Rivers Trust already undertakes extensive fisheries monitoring across the South West, including electrofishing surveys using methodologies similar to those employed by the Environment Agency
  • However, fish classification under the Water Framework Directive is currently based on formal Environment Agency monitoring data. While fisheries data collected by third parties is routinely shared with the Environment Agency and may be used to inform wider fisheries management decisions, it is not generally relied upon directly for Water Framework Directive classification purposes
  • As a result, the purpose of this intervention is not to replace statutory Environment Agency monitoring. Instead, it is to generate sufficient evidence to challenge current assumptions, identify where classifications may no longer reflect river conditions, and support the case for updated Environment Agency monitoring during the next Water Framework Directive assessment cycle
  • The Environment Agency has already recognised that fish classifications may be unreliable in a number of river water bodies. We have identified nine river water bodies where suspect fish data may be contributing to current classifications and where updated evidence could materially affect ecological status assessments.
  • Compared with many other restoration interventions, this represents a relatively low-cost and potentially high-impact opportunity. If updated monitoring demonstrates that fish populations are healthier than current classifications suggest, a number of river water bodies could potentially achieve Good Ecological Status without requiring additional physical restoration measures.
  • There is currently no dedicated funding programme for this activity. Delivery would require a relatively modest investment through fisheries programmes, catchment partnership funding, charitable grants, research funding or direct support from the Environment Agency

Fish Data River Water Bodies

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Badgworthy Water £6,000 £0 No No WRT
Farley Water £6,000 £0 No No WRT
Hookmoor Brook £6,000 £0 No No WRT
Huntacott Water £6,000 £0 No No WRT
Lower East Lyn River £6,000 £0 No No WRT
Lower River Yeo (Barnstaple) £6,000 £0 No No WRT
Pulworthy Brook £6,000 £0 No No WRT
Upper East Lyn River £6,000 £0 No No WRT
West Lyn River £6,000 £0 No No WRT

8. Removing barriers

Removing barriers
DescriptionRestore ecological connectivity by removing, modifying or bypassing structures that restrict the movement of fish and other aquatic species.
Lead delivery organisationWest Country Rivers Trust, Environment Agency
No. of river water bodies7
Estimated total cost£3.5m
Funding available£0
Funding gap£3.5m
Funding route / sourceEnvironment Agency, river restoration programmes, water company catchment investment, National Lottery, charitable trusts, environmental grants and private finance.
Ecological benefitImprovement in fish populations and other benefits arising from restored ecological connectivity and flow.
Confidence in costingsLow-medium

Progress

  • The Westcountry Rivers Trust and Environment Agency already undertake fish passage and river restoration projects across the South West, meaning the technical expertise and delivery mechanisms are well established
  • We have identified seven river water bodies where fish passage appears to be a significant constraint on achieving Good Ecological Status. However, delivery costs remain highly uncertain until individual structures have been assessed and options developed
  • Experience elsewhere demonstrates that costs vary considerably depending on the size of the structure, ownership, engineering complexity and consenting requirements. Individual projects can range from relatively simple removals to multi-million-pound engineering schemes
  • The immediate priority is therefore assessment, option appraisal and project development. This will create a pipeline of investable projects and improve confidence in future cost estimates
  • There is currently no dedicated funding programme for these barriers. Delivery is expected to rely on a combination of Environment Agency funding, river restoration programmes, charitable grants, National Lottery funding, water company catchment investment and private finance

Removing Barriers - Priority River Water Bodies

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradiford Water £500,000 £0 No No WRT
Dalch £500,000 £0 No No WRT
Farley Water £500,000 £0 No No WRT
Heddon £500,000 £0 No No WRT
Knowl Water £500,000 £0 No No WRT
Lower River Yeo (Barnstaple) £500,000 £0 No No WRT
Wagaford Water £500,000 £0 No No WRT

9. Special case interventions

Special case interventions
DescriptionAddress localised and non-standard environmental pressures, including mining impacts, specific pollutants, low/no flow, heavily modified water bodies and other complex ecological issues.
Lead delivery organisationVaries
No. of river water bodies8
Estimated total cost£2m
Funding available£0
Funding gap£2m
Funding route / sourceSite-specific combination of public funding, regulatory investment, environmental grants and private finance.
Ecological benefitIntervention specific.
Confidence in costingsLow

Progress

  • We have identified 8 river water bodies where failure appears to be driven by localised or non-standard pressures that do not fit within the main intervention pathways identified through Catchment Catalyst
  • These include issues such as historic mining impacts, specific pollutants, low or no flow conditions, heavily modified channels and other complex ecological pressures that require bespoke assessment and response
  • Unlike wastewater, agricultural runoff or fish passage interventions, there is no standard delivery model for these river water bodies. Each case requires investigation to understand the root causes of failure and identify appropriate solutions
  • The immediate priority is therefore feasibility, evidence gathering and option appraisal to improve understanding of costs, benefits and delivery mechanisms
  • Funding routes are also likely to vary significantly between sites and may include regulatory investment, public-sector funding, environmental grants, charitable funding and private finance, depending on the nature of the pressure being addressed
  • Given the complexity and diversity of these cases, cost estimates and delivery pathways remain less certain than for other intervention areas. As a result, further investigation should be considered the first phase of delivery

Special Case Interventions

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Lower River Mere – active mine impacts £250,000 £0 No No To establish
Lower River Yeo (Barnstaple) – low flow, trade/industry discharge £250,000 £0 No No To establish
Pulworthy Brook – low flow £250,000 £0 No No To establish
Rye Stream – regulating reservoir regime £250,000 £0 No No To establish
Taw Estuary – heavily modified with flood protection structures £250,000 £0 No No To establish
Venn – specific pollutants £250,000 £0 No No To establish
Wagaford Water – low flow, trade/industry discharge £250,000 £0 No No To establish
West Okement – abandoned mine, natural mineralisation £250,000 £0 No No To establish

10. Riparian tree planting

Riparian tree planting
DescriptionEstablish and restore woodland alongside rivers to improve habitat quality, reduce runoff and sediment delivery, increase shading and improve ecosystem resilience.
Lead delivery organisationNorth Devon Biosphere Foundation
No. of river water bodies48
Estimated total cost£2.7 million
Funding available£2.7 million
Funding gapNone
Funding route / sourceEnglish Woodland Creation Offer (EWCO)
Ecological benefitIncreased river shading reduces algal growth, improves water temperature resilience, reduces bank erosion and supports ecological recovery.
Confidence in costingsMedium

Progress

  • The North Devon Biosphere Foundation, through the Devon Woods programme, already has an active delivery mechanism for woodland creation across Northern Devon. This provides an established platform for identifying opportunities, engaging landowners and supporting applications for woodland grants
  • Funding is available through the Forestry Commission's England Woodland Creation Offer (EWCO), which provides support for woodland establishment and long-term maintenance. As a result, unlike many other interventions, a recognised and funded delivery route already exists
  • We have therefore classified the full £2.7 million investment requirement as available, as the principal funding mechanism is already in place. The key challenge is not securing grant funding but generating sufficient landowner participation and targeting woodland creation towards the highest-priority river water bodies
  • The priority should be to focus woodland creation within river water bodies where riparian planting can deliver the greatest ecological benefit, including locations affected by nutrient enrichment, elevated algal growth, limited channel shading and poor habitat resilience
  • Additional incentives may further increase uptake. In particular, opportunities to combine EWCO support with woodland carbon revenues, biodiversity funding and water-company catchment investment could improve the attractiveness of projects to landowners and accelerate delivery
  • While some continuation funding will be required to maintain the advisory capacity provided through Devon Woods, the delivery model, funding route and implementation mechanisms are already established, making this one of the most delivery-ready interventions

Riparian Tree Planting

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River 2.4km (9.6km) £48,000 £48,000 No No ND Biosphere Foundation
Bradwell Stream 1.3km (5.0km) £26,000 £26,000 No No ND Biosphere Foundation
Bullow Brook 1.5km (6.1km) £30,000 £30,000 No No ND Biosphere Foundation
Burcombe Stream 1.1km (4.2km) £22,000 £22,000 No No ND Biosphere Foundation
Chelfham Stream 1.1km (4.5km) £22,000 £22,000 No No ND Biosphere Foundation
Combe Lake 0.6km (2.6km) £12,000 £12,000 No No ND Biosphere Foundation
Cookbury Stream 1.9km (7.4km) £34,200 £34,200 No No ND Biosphere Foundation
Crooked Oak 4.4km (17.4km) £88,000 £88,000 No No ND Biosphere Foundation
Dalch 4.2km (16.9km) £84,000 £84,000 No No ND Biosphere Foundation
Dolton Stream 0.8km (3.2km) £16,000 £16,000 No No ND Biosphere Foundation
Duntz 3.8km (15.0km) £76,000 £76,000 No No ND Biosphere Foundation
Hawkridge Brook 2.1km (8.5km) £42,000 £42,000 No No ND Biosphere Foundation
Hole Brook 2.8km (11.2km) £56,000 £56,000 No No ND Biosphere Foundation
Hollocombe Water 2.8km (11.0km) £56,000 £56,000 No No ND Biosphere Foundation
Huntshaw Water 2.0km (7.9km) £40,000 £40,000 No No ND Biosphere Foundation
Iddesleigh Stream 0.7km (2.9km) £14,000 £14,000 No No ND Biosphere Foundation
Kenwith Stream 1.0km (4.1km) £20,000 £20,000 No No ND Biosphere Foundation
Knighty Brook 2.1km (8.5km) £42,000 £42,000 No No ND Biosphere Foundation
Langham Lake 3.5km (13.9km) £70,000 £70,000 No No ND Biosphere Foundation
Langtree Lake 1.9km (7.5km) £38,000 £38,000 No No ND Biosphere Foundation
Little Mere River 1.2km (4.8km) £24,000 £24,000 No No ND Biosphere Foundation
Little Silver Stream 3.0km (11.9km) £60,000 £60,000 No No ND Biosphere Foundation
Lower Caen 1.4km (5.4km) £28,000 £28,000 No No ND Biosphere Foundation
Lower Little River Dart 5.0km (19.8km) £100,000 £100,000 No No ND Biosphere Foundation
Lower River Lew (Torridge) 1.4km (5.7km) £28,000 £28,000 No No ND Biosphere Foundation
Lower River Okement 0.9km (3.6km) £18,000 £18,000 No No ND Biosphere Foundation
Lower River Yeo (Bideford) 1.0km (4.0km) £20,000 £20,000 No No ND Biosphere Foundation
Lower River Yeo (Lapford) 1.3km (5.2km) £26,000 £26,000 No No ND Biosphere Foundation
Mole (Bray to Yeo) 2.3km (9.3km) £46,000 £46,000 No No ND Biosphere Foundation
Mole (Source to Burcombe Stream) 4.3km (17.2km) £86,000 £86,000 No No ND Biosphere Foundation
Mole (Taw to Bray) 3.6km (14.2km) £72,000 £72,000 No No ND Biosphere Foundation
Mole (Yeo to Burcombe Stream) 0.9km (3.6km) £18,000 £18,000 No No ND Biosphere Foundation
Mully Brook 2.2km (8.8km) £44,000 £44,000 No No ND Biosphere Foundation
Mussel Brook 2.1km (8.4km) £42,000 £42,000 No No ND Biosphere Foundation
Nadrid Water 2.0km (8.0km) £40,000 £40,000 No No ND Biosphere Foundation
Newton Tracey Stream 0.6km (2.2km) £12,000 £12,000 No No ND Biosphere Foundation
Taw (Bullow Brook to River Yeo) 1.6km (6.2km) £32,000 £32,000 No No ND Biosphere Foundation
Taw (Little Dart River to River Mole) 1.6km (6.5km) £32,000 £32,000 No No ND Biosphere Foundation
Taw (River Mole to Estuary) 4.9km (19.5km) £98,000 £98,000 No No ND Biosphere Foundation
Taw (River Yeo to Little Dart River) 2.2km (8.9km) £44,000 £44,000 No No ND Biosphere Foundation
Taw (Source to Bullow Brook) 7.6km (30.2km) £152,000 £152,000 No No ND Biosphere Foundation
Torridge (Combe Lake to Lew) 5.1km (20.6km) £120,000 £120,000 No No ND Biosphere Foundation
Torridge (Dipple Water to Combe Lake) 3.2km (12.9km) £64,000 £64,000 No No ND Biosphere Foundation
Torridge (Lew to Estuary) 11.2km (44.8km) £224,000 £224,000 No No ND Biosphere Foundation
Upper River Mere 2.4km (9.5km) £48,000 £48,000 No No ND Biosphere Foundation
Upper River Yeo (Bideford) 3.6km (14.5km) £72,000 £72,000 No No ND Biosphere Foundation
Upper River Yeo (Lapford) 6.3km (24.9km) £126,000 £126,000 No No ND Biosphere Foundation
Waldon 7.8km (23.1km) £156,000 £156,000 No No ND Biosphere Foundation
Whiteleigh Water 2.0km (7.8km) £36,000 £36,000 No No ND Biosphere Foundation
Whitsleigh Down Brook 0.9km (3.4km) £18,000 £18,000 No No ND Biosphere Foundation

11. Fish habitat improvement

Fish habitat improvement
DescriptionImprove river habitat quality for fish through restoration of spawning habitat, in-channel features, river margins and natural river processes.
Lead delivery organisationWest Country Rivers Trust
No. of river water bodies7
Estimated total cost£400k
Funding available£0
Funding gap£400k
Funding route / sourceEnvironment Agency fisheries programmes, river restoration programmes, water company catchment investment, charitable trusts, environmental grants and private finance.
Ecological benefitDirect improvement in fish habitat quality, supporting increased spawning success, juvenile recruitment and population resilience.
Confidence in costingsLow-medium

Progress

  • The Westcountry Rivers Trust already delivers fish habitat improvement projects across Northern Devon and the wider South West, including gravel augmentation, woody debris introduction, bank restoration, channel diversification and other measures designed to improve habitat quality for salmonids and other fish species
  • As a result, the technical expertise, delivery partnerships and practical methods required to implement this intervention are already well established. The challenge here is securing funding to expand activity within the six priority river water bodies
  • There is currently no dedicated long-term funding programme available to deliver fish habitat improvements at scale. Delivery is therefore expected to rely on a combination of Environment Agency fisheries programmes, river restoration funding, water company catchment investment, charitable trusts, environmental grants and private finance

Fish Habitat Improvement - Priority River Water Bodies

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Bradiford Water £50,000 £0 No No WRT
Cookbury Stream £50,000 £0 No No WRT
Farley Water £50,000 £0 No No WRT
Heddon £50,000 £0 No No WRT
Lower River Yeo (Barnstaple) £50,000 £0 No No WRT
Rye Stream £50,000 £0 No No WRT
Wagaford Water £50,000 £0 No No WRT
Whiteleigh Water £50,000 £0 No No WRT

12. Private sewerage awareness & improvement programme

Private sewerage awareness & improvement programme
DescriptionImprove the management of private sewerage systems through awareness campaigns, advice, inspections and support for repairs and upgrades.
Lead delivery organisationTo be established
No. of river water bodies17
Estimated total cost£170,000
Funding available£0
Funding gap£180,000
Funding route / sourceNot yet clear
Ecological benefitReduce diffuse nutrient pollution from private sewerage systems and support improved phosphate status.
Confidence in costingsLow-medium

Progress

  • There is currently no dedicated programme or lead organisation focused on identifying and addressing private sewerage impacts within priority river water body catchments.
  • We have identified 18 river water bodies where private sewerage systems may be contributing to water quality pressures. However, further investigation is likely to be required before the scale of the problem, and the most cost-effective interventions, can be fully understood
  • Potential delivery partners could include local authorities, the Environment Agency, catchment partnerships, water companies and environmental NGOs. However, no delivery mechanism has yet been established
  • At present there is no dedicated funding route for this intervention. Further work is required to identify potential funding sources and delivery partners, although the relatively modest scale of investment required suggests that a targeted awareness and improvement programme may be achievable through a combination of public funding, charitable grants and catchment partnership investment
  • Given the relatively low cost of intervention and the potential for cumulative improvements across multiple catchments, a pilot programme focused on a small number of priority river water bodies may represent an effective first step

Private Sewerage Awareness & Improvement Programme

River Water Body Size of Intervention Estimated Cost Funding Available Started Delivery Finished Delivery Lead
Abbey River £10,000 £0 No No tbd
Coney Gut £10,000 £0 No No tbd
Dolton Stream £10,000 £0 No No tbd
Horwood Stream £10,000 £0 No No tbd
Kenwith Stream £10,000 £0 No No tbd
Knighty Brook £10,000 £0 No No tbd
Knowl Water £10,000 £0 No No tbd
Lower Caen £10,000 £0 No No tbd
Lower River Yeo (Barnstaple) £10,000 £0 No No tbd
Lower River Yeo (Bideford) £10,000 £0 No No tbd
Lower River Yeo (Lapford) £10,000 £0 No No tbd
Middle River Okement £10,000 £0 No No tbd
Mole (Yeo to Burcombe Stream) £10,000 £0 No No tbd
Nadrid Water £10,000 £0 No No tbd
Torridge (Lew to Estuary) £10,000 £0 No No tbd
Venn £10,000 £0 No No tbd
West Lyn River £10,000 £0 No No tbd

Community Action

Biosphere Partnership organisations are leading on many community engagement projects across the North Devon catchment. Some of these are explicitly related to water quality whereas others may focus on other aspects, such biodiversity or wellbeing, but these projects often include actions that will help improve our rivers.

The Biosphere is currently progressing a large public engagement project called Healthy Rivers. Working with the Taw & Torridge River Champions, we are linking together the existing rivers groups across North Devon, and identifying where gaps exist and creating new groups where needed. We are offering training on water testing, using similar kit to that used by Westcountry Rivers Trust, so that new Citizen Scientists can monitor their local river. The collected will be uploaded to the Smart Biosphere where it will be publicly available for analysis and download.

What can you do now to improve water quality?

  • Walk your local river and report any issues. Pollution should be reported to the Environment Agency on 0800 807060
  • Always bag and bin dog waste.
  • Use eco cleaners around your house.
  • Stop using fabric softener; generally these chemicals are not removed by treatment works.
  • Create a "rain garden". By diverting downpipes onto your garden, you can slow water flow into the sewer system and reduce the risk of sewage overflows.
  • Add water butts to your downpipes to reduce water usage and thereby keep more water in our rivers.
  • Remove litter from rivers and beaches.
  • Stop using pesticides in your garden.
  • Avoid/reduce the use of flea treatments for pets.
  • Support campaigns for improving water quality.